rules, hand-built from 3 of your completed jobs. Each carries the standard behind it and what skipping it cost. Every closed job adds to this number.

36 of 36 rules

  • KB-001

    Check every adjacent space

    High

    Take a moisture reading in every room sharing a wall, floor cavity, or ceiling plane with an affected room before closing that room.

    Trigger: any room marked affected

  • KB-002

    Water travels along the framing, not the floor

    High

    Where a loss originates at an exterior wall, check the sill plate along the full run of that wall, not just below the visible damage.

    Trigger: source of loss is exterior, ice, or intrusion

  • KB-003

    One failure point can reach six rooms

    High

    For a mechanical failure (HVAC, supply line, drain), trace the run of the line and check every room it passes through or under.

    Trigger: source of loss is HVAC, plumbing, or appliance

  • KB-004

    Contents are a separate line

    Advisory

    If contents must be moved to access the affected area, record it. It bills separately from mitigation.

    Trigger: any room with contents present

    Adds: CONTENT_MANIP, CONTENTS_MOVE_RESET

  • KB-005

    Structure age gates demolition

    Blocking

    For any structure built before 1981, identify suspect asbestos-containing materials and test before disturbing them. Demolition cannot begin until results are back.

    Trigger: structure.yearBuilt < 1981 AND any tear-out selected

    Adds: ASBESTOS_SURVEY_BASE, ASBESTOS_SAMPLE

  • KB-006

    Suspect material list

    High

    Flag 9" or 12" floor tile, sheet vinyl and its backing, popcorn or textured ceiling, pipe and duct wrap, and joint compound in pre-1981 structures.

    Trigger: structure.yearBuilt < 1981

  • KB-007

    Under 1% is not regulated

    Advisory

    When a composite analysis returns below 1%, the material is not regulated ACM. Do not scope abatement for it, and do record the result.

    Trigger: an asbestos result below 1% exists

  • KB-008

    Cause of loss must be photographed on day one

    High

    Before leaving the first visit, capture the point of entry, the path of water, the full affected elevation, and the roof or gutter line where relevant.

    Trigger: source of loss is exterior, storm, ice, or intrusion

  • KB-009

    Opening a cavity commits you to cleaning it

    High

    If you drill, cut, or otherwise open a wall cavity on a Category 2 or 3 loss, scope cavity cleaning: HEPA vacuum and clean stud wall, or record why not.

    Trigger: drillHoles > 0 OR floodCut = true AND category >= 2

    Adds: HEPA_VAC_DETAILED, CLEAN_STUD_WALL

  • KB-010

    Cavity drying or flood cut, decide on purpose

    High

    Choose in-place cavity drying or a flood cut explicitly and record the reason. They produce different scopes and different drying times.

    Trigger: wet wall cavity confirmed

  • KB-011

    Category escalation is an event, not an opinion

    High

    Escalating category requires a reason code, a photograph, and a timestamp. It changes the tear-out line items, the PPE, and the containment requirement.

    Trigger: user proposes a category change

  • KB-012

    Microbial growth escalates the category

    High

    Visible microbial amplification on structural materials escalates the loss to Category 3. Confirm and record before proceeding.

    Trigger: technician marks a photo as showing microbial growth

  • KB-013

    Category 3 changes your tear-out lines

    Advisory

    On Category 3, tear-out lines take the Cat 3 rate and materials are bagged for disposal rather than salvaged.

    Trigger: category = 3

  • KB-014

    Category 3 requires PPE on the invoice

    High

    On Category 3, scope PPE, respirators, cartridges and HEPA filters. They are billable and they are expected by the carrier.

    Trigger: category = 3

    Adds: PPE_HAZ, PPE_GLOVES, RESPIRATOR_FULL_FACE, RESPIRATOR_CARTRIDGE, HEPA_FILTER_VAC

  • KB-015

    Containment on Category 3

    High

    Category 3 work areas require containment with a decon chamber or airlock, and negative air where microbial growth is present.

    Trigger: category = 3

    Adds: CONTAINMENT_BARRIER, TENSION_POST, PEEL_SEAL_ZIPPER, NEG_AIR_LARGE, HEPA_FILTER_NEG_AIR

  • KB-016

    Every affected material class needs a point

    High

    Place at least one monitoring point in each material class you intend to bill tear-out or drying for.

    Trigger: tear-out scoped for a material with no corresponding monitoring point

  • KB-017

    Unaffected baseline is mandatory

    High

    Record a dry-standard reading in an unaffected area of the same material before setting drying goals.

    Trigger: always, once any room is marked affected

  • KB-018

    Daily monitoring, or a written reason

    High

    Take readings daily while equipment is on site. If a day is missed, write the reason into the monitoring log, not into the estimate.

    Trigger: daysSinceLastReading >= 1 with active equipment

  • KB-019

    Stabilization holds must be justified in the field record

    High

    If equipment runs in a hold pattern (pending testing, access, or approval), record the reason daily in the monitoring log.

    Trigger: equipment active AND a blocking gate is unresolved

  • KB-020

    Photograph the meter with the reading visible

    Advisory

    Every moisture reading needs a photo showing the meter display and the material it is on.

    Trigger: any reading recorded

  • KB-021

    Match the equipment to the calculator

    High

    Compare placed equipment against the calculated recommendation before leaving. Under-equipping extends the job, and every extra day is a day the carrier can question.

    Trigger: placedAirMovers < recommendedMin OR placedDehuCapacity < ahamRecommended

  • KB-022

    Size the dehumidifier from chamber volume and class

    High

    Calculate AHAM pints per day from the chamber volume and class of water, and place capacity at or above it.

    Trigger: always, at the equipment step

  • KB-023

    Photos must be attached to something

    High

    Every photo lands in a typed slot bound to a room, a material, and a checklist item.

    Trigger: always

  • KB-024

    Required photo slots per room

    High

    Each affected room needs, at minimum, an overview, a damage detail, a meter-in-frame shot, and a material transition shot.

    Trigger: any room marked affected

  • KB-025

    Signed authorization before work begins

    High

    Work authorization must be signed before mitigation starts.

    Trigger: always, before the job can move to active

  • KB-026

    Name the adjuster and the project manager

    Advisory

    Capture the adjuster name and direct contact, and assign a project manager, at intake.

    Trigger: always

  • KB-027

    Record the price list version at intake

    Advisory

    Capture the Xactimate price list version for the zip and month of service at the start of the job.

    Trigger: always

  • KB-028

    Note pre-existing damage before you touch anything

    High

    Photograph and describe pre-existing damage and construction defects at intake.

    Trigger: always

  • KB-029

    Emergency call timing changes the rate

    Advisory

    Record the actual arrival time. After-hours arrival bills at a materially higher rate.

    Trigger: always

  • KB-030

    Separate regular from after-hours labour

    Advisory

    Log setup, take-down, monitoring and travel hours split by regular and after-hours.

    Trigger: always

  • KB-031

    Every point reaches goal or carries an exception

    High

    A room cannot be closed while any monitoring point sits above its drying goal.

    Trigger: anyPoint.reading > dryingGoal at completion

  • KB-032

    Confirm before pulling equipment

    High

    Take a final confirming reading at every point before equipment is removed.

    Trigger: user attempts to mark equipment removed

  • KB-033

    No job closes with an open point

    High

    A job cannot be marked complete while a monitoring point has no final status.

    Trigger: anyPoint.status = 'unknown' at completion

  • KB-034

    Photograph equipment placement and removal

    Advisory

    Photograph each unit in place at setup and record placement and removal timestamps.

    Trigger: equipment added

  • KB-035

    Capture the reconstruction lead on site

    Advisory

    Before leaving the final visit, ask about reconstruction and record the answer.

    Trigger: job marked complete

  • KB-036

    Mitigation pricing is a range, not a quote

    High

    Present a range with its drivers named. Do not present a fixed mitigation price on site.

    Trigger: always, at the scope step